Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

DBNPL Project

Asset Planning Engineer, Avinash EM Projects (p) Ltd., DBNPL Project

START Date: 
March, 2011
END Date: 
December, 2013
  • Construction Services of Cross Country Pipe Line to Gail (I) Limited, India, for Dadri Bhawana Nangal Pipe Line Project (DBNPL) consist of pipeline of 8 & 16 inch and combined length of 116 Kms.
Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
0