Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Changshu 2×300MW Unit Desulfurization Reform Project

Electrical person in charge, SPIC Yuanda Environmental Protection Engineering Co.,Ltd., Changshu 2×300MW Unit Desulfurization Reform Project

START Date: 
April, 2012
END Date: 
June, 2013

project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance

Electrical person in charge, SPIC Yuanda Environmental Protection Engineering Co.,Ltd., Changshu 2×300MW Unit Desulfurization Reform Project

START Date: 
April, 2012
END Date: 
June, 2013

project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance

Electrical person in charge, SPIC Yuanda Environmental Protection Engineering Co.,Ltd., Changshu 2×300MW Unit Desulfurization Reform Project

START Date: 
April, 2012
END Date: 
June, 2013

project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance

Electrical person in charge, SPIC Yuanda Environmental Protection Engineering Co.,Ltd., Changshu 2×300MW Unit Desulfurization Reform Project

START Date: 
April, 2012
END Date: 
June, 2013

project name:Changshu 2×300MW Unit Desulfurization Reform Project
Served as a full-time electrical post in the project, and began to contact the project manager's daily work of various conversions, and successfully completed 168 trials of Changshu 2×300MW units (including economizer transformation, air preheater transformation, and induction and increase integration transformation). Transported the project and successfully passed the environmental protection acceptance

Market Place