Cable Lying from Abarak to Rasgtc (Qatar)

Project Planning Engineer, LX CABLES Engineering Qatar, Cable Lying from Abarak to Rasgtc (Qatar)

START Date: 
February, 2010
END Date: 
February, 2011

Collection and collation of activities from different phase of deliverable engineers

Developed project plans and schedules and accurate milestone reports

Established resource loaded planning schedules

Providing timely reports on activity against schedule and project risk

(Bi)/Weekly/Monthly reports generation including ā€˜S’-curves for client & Management review.

Identifying, monitoring& streamlining of critical paths running through the Project Schedule and individual contracts.

Project Planning Engineer, LX CABLES Engineering Qatar, Cable Lying from Abarak to Rasgtc (Qatar)

START Date: 
February, 2010
END Date: 
February, 2011

Collection and collation of activities from different phase of deliverable engineers

Developed project plans and schedules and accurate milestone reports

Established resource loaded planning schedules

Providing timely reports on activity against schedule and project risk

(Bi)/Weekly/Monthly reports generation including ā€˜S’-curves for client & Management review.

Identifying, monitoring& streamlining of critical paths running through the Project Schedule and individual contracts.