Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Hydro Electric Commission Tasmania

CONSTRUCTION MANAGER, Hydro Electric Commission Tasmania, Lower Pieman Dam and King River Scheme

START Date: 
September, 1984
END Date: 
February, 1987

The Lower Pieman Dam is a 1.75 million cubic metre concrete faced rock fill dam on the West Cost of Tasmania. In charge of the construction of the dam as the project drew to completion. Commenced as site engineer in charge of the construction of the spillway. Over a period of two years promoted Senior Site Engineer. Responsible for all construction activities, with four engineers and 400 men on site. Gained experience in the following construction activities; roads, bridges, reinforced concrete, slipforming, grouting and bulk earthworks.

Experience Hours (Planning & Scheduling): 
500

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content