Started with development of coding structure for consortium and level 3 programs for “Saldanha Mechanical Contractors”, written in Primavera ver 2.b. This contractual program had to be integrated with other contractors on site due to the fast track nature of the project and had to be totally network compatible so that all contractors on site could update one integrated schedule. This schedule became contractual level 3 programs for the consortium.