 Tunnel Advance Rates (m/day)

Tunnel In London Clay  
ID < 7.0 m 2.5 - 3.0 m/day
ID 7.0 - 10.0 m 1.5 - 2.5 m/day
ID > 10.0 m 1.0 - 1.5 m/day
Tunnel In Woolwich & Reading Beds  
ID < 7.0 m 1.5 - 2.0 m/day
ID 7.0 - 10.0 m 1.5 m/day
ID > 10.0 m 1.0 m/day
Inclined Tunnels  
ID < 7.0 m 2.0 m/day
ID 7.0 - 10.0 m 1.0 m/day
Vertical Shafts  
ID < 9.0 m 1.5 m/day
ID 9.0 - 15.0 m 1.0 m/day
Circulation Halls 1 m of hall circumference/day.
Excavation Of Junctions 1 junction in 6 days = 0.17 m/day
  Secondary Tunnel Lining Rates  
Tunnels  
ID < 6.5 m 2.5 m/day
ID > 6.5 m 2.0 m/day
Inclined Tunnels  
ID < 6.0 m 2.0 m/day
ID > 6.0 m 1.5 m/day
Vertical Shafts  
ID < 9.0 m 2.0 m/day
ID > 9.0 m 2.5 m/day
Circulation Halls  
ID 11.0 m 2.0 m/day
Intermediate Landings  
With Columns 2.0 m/day and individual tunnel
Without Columns 2.0 m/day
Junctions 1 junction in 4 days = 0.25 m/day