Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Controller, Kentz Canada Limited, Forthhills

START Date: 
May, 2014

• Developed integrated schedules using Primavera for smal projects and their different stages

• Interfaced the schedule with the project budget and resource load it with labor and material resources based on the project approved budget hours and quantity.

• Liaise with management team to ensure all project tasks are identified and resource needs are properly estimated for the project.

• Updated project schedule, monitor actual progress and compare the updates with the baseline and report progress against schedule in the proper format.

• Prepared weekly and monthly reports, progress profiles and any other schedule related status reports

• Reviewed project scope change and change order requests for proper justification, cost and schedule impacts, and adequate budget and funding

• Provide direction and focus to all project cost control and change management efforts.

• Present Cost data formats and reports for Management review

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500