Responsible for creating and managing schedule from 30 contractors mainly Rides an Attractions, Had to coordinate with the Main Project Managers, Worked for Jack Rouse Associates (Consultants) who hired Blair Anderson to carry out Planning Services.

 

M.A.Kharafi & Sons (Contractor) hired Blair Anderson to carry out Planning Services for the project. Preparing the baseline programme, Monthly programme updates, Preparing Claim notifications, Interim particulars, Correspondence etc. preparing revised programme, time impact analysis, and claim report. Etc.

 

GTS Installation and Maintenance LLC (Contractor) hired Blair Anderson to carry out Planning Services for the project. Preparing the baseline programme, Monthly programme updates, Preparing Claim notifications, Interim particulars, Correspondence etc. preparing revised programme, time impact analysis, and claim report. Etc.

Preparing the Time Impact Analysis for Contractors

Preparing Delay notifications

Forensic Analysis using different methods like As Planned Impact Analysis, As Build Impact Analysis. Window Analysis

 

Preparing the Claim Programmes, Reviewing the Claim Programme.

Preparing Claim Write up, compiling delay notice, advising client from time to time for delay notifications etc