Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planner, Engineer Planner /Scheduler /Quantity Surveyor, Waad Project, Waad Project

START Date: 
April, 2007
END Date: 
March, 2011

250 Buildings, over $500 million budget

• Personal assistant to Chief Financial Officer.

• Planning and Scheduling: Master planning, financial planning, resource planning and management, implementing design submittal coordination, baselines, updates, progress reports, planning revisions.

• Estimating Cost: Cost estimation and budget preparation, and implementation for estimation and cost control procedures and systems.

• Quantity Surveying: Specifications of items, bills of quantities, change management tracking, implementation of quantity surveying procedures, taking off Structural and Finishing Quantities, and made quantity surveying software.

• Contracts Management: Tender conditions and tender documents reparation, contracts management in progress, and change management tracking.

• Worked with many contractors, and consultants as follows:

Project Description: Rebuilding of 250 residential/ commercial buildings, each building consists of 12 to 17 stories, $500 million project, in Beirut Southern Suburbs.

Contractors: Al-Inmaa, Al Amir, Kodeih, Beam Developpers, Bonian, Ebco-Bitar,Hasib Ibrahim, Engineering Touch, Haicon Mrad, Hammood, RYC, Safi Eddine, Safa, Studies, Tajco, TDC, Tower, UCC, UMA, UNA, Urtec, Zerock, Zolfikar Outhman.

Consultants: Getti, Almadaen, Arch, Idea, Abdul Wahed Shehab, Ma Consult, AEG.

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
2000