Project Engineer, KOC, Various
START Date:
August, 1993
END Date:
August, 2007 Kuwait Oil Company Aug 1993-Aug 2007
Project Engineer Kuwait
Managed multi-discipline fixed price LSTK civil and mechanical projects from inception to completion; values ranged between USD $1 Million to $20 Million. Experienced all aspects of project management with specific emphasis on planning and scheduling. Projects examples:
- Revamping of CRU at GC-04 - SK
- GC-04 New Control Room
- GC-15 Rehabilitation Project - NK
- Installation of Corrosion Monitoring Facilities
- Dredging of Small Boat Harbor at Mina Al-Ahmadi
- Marine Maintenance Building at Small Boat Harbor
- Refurbishment of North Tank Farm and South Tank Farm
- Review and vet contractors and sub-contractors schedules, ensure its reasonableness to achieve the projects planned completions
- Verify and endorse contractor invoices based on actual percent complete of activities
- Review and validate contractor’s timesheet where applicable. Calculate and give feedback on productivity factors and progress payments
- Review and approve contractor requests for time extension based on authorized change orders and /or authorized suspension of works
- Record and maintain all schedule changes for claims analysis, if needed