March 2012 – Till Present

Planning Engineer

Celik Is LLC, Oman

Responsibility

 B

reaking down the construction activities into progress measurable elements.

 Preparing Site Instruction impact analysis for claiming Extension of Time.

 Involved in the preparation of revised construction schedule.

 Contribute in preparing narrative summary for progress reports.

 Preparing progress monitoring formats for site engineer and supervisors reports.

 Follow-up of with deliverables (materials and drawings) and their impact on the schedule.

 Prepare Look Ahead Schedules to prioritize resources be able to catch-up contract program

 Contribute in preparing narrative summary for progress reports

 Update construction schedule.

January 2010 – January 2012

Project Manager

Engineering Innovation Design & Consulting, Oman

Responsibility

 Heading all construction activities on site.

 Decision making on behalf of client.

 Quality Management, Planning, scheduling of the concerned site.

 Negotiation and resolve claims associated with delays, additional cost and time.

 Preparing Project Status Reports.

 Completing project with the stipulated budget and time.

Projects Handled: Radisson Blu hotel (5 star), Buraimi court complex (Ministry of Oman)

January 2007 – August 2008

Project Coordinator

SEA INDIA SOLUTIONS LLC, India

Responsibility

Planning, scheduling and tracking of activities for commercial and residential projects.

 Heading the design team adapting to quick and effective design methodology to ensure qualitative results.

 Providing valuable inputs and reminders to the client.

 Negotiation and resolve claims associated with delays, additional cost and time.

 Preparing Project Status Reports.

Projects Handled: Re- branding of major institutions including BARCLAYS, MORRISONS, BOOTS, SAINSBURY and TESCO all in UK.

July 2006 – December 2006

Architect

INDIGO INCORPORATED, India

Responsibility

Heading the conceptual stage based on which the preliminary design is made.

 Design discussion and design presentation with the clients at different levels to ensure quick and effective designing.

 The evolution of the final design and ways of execution.

 Co-ordination with various services, Structural Consultants, contractors and clients.

December 2004 – May 2005

Trainee Architect

"AN ARCHITECTURE OFFICE", Goa, India

Responsibility

Site visits to check the drawings.

 Developing conceptual designs.

 Drafting of plan, section and elevations.

 Assisting the project manager in project planning.