Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

PROJECT/ SITE ENGINEER, MICCO, LANSH ENGINEERING, 1) BIRLA COPPER III, DAHEJ GUJARAT, 2) BHUSHAN STEEL, JHARSAGUDA,ORISSA

START Date: 
August, 2003
END Date: 
June, 2007

 

Direct Project Execution & Site Management:

·         Prepare & Organize the resources required to complete the Project as per the Scope and progress committed in PO & attached Bar chart.

·         Ensure the mobilized team and machinery was competitive to engage them in the project.

·         Daily planning and organizing the site activities in accordance with Erection schedule / bar chart submitted to client.

·         Played active part in Basic surveying of land & marking layout before initiating civil works of plant footings.

·         Follow the correct procedure of work and ensure all items fabricated/ erected as per drawings provided and undergo modification after getting clearance from client and consultants.

·         After completion of tasks, work is inspected/ checked by physical measurement, Ultrasonic & Radiography tests, Dye penetrant test and Hydro-tests.

·         Follow manpower safety and procedure during site work with Proper utilization of site resources.

·         Timely completion of projects within budgeted expenditure and safety with good workmanship.

·         Timely correspondence of site progress and changes to Client and Project Manager.

·         Take plant trails and commissioning as per manuals or procedure and make record of tests conducted.

Identify and closure of all Non Conformities raised by consultant/ client and handover the plant to client.