Planning Engineer, Foster Wheeler International Corporation , Thailand Propylene Oxide Project
Total of Man- hours 5,221,876
- Yard progress verification: analysis of Sub-Contract claimed progress against FWW verified CMS progress.
- Programmed of Work , Progress “S” Curve, Manpower histogram (By trade).
- Progress, Man-hour & Productivity Report , Progress Evaluation Summary Report.
- Three Week Look-ahead schedule, Weekly Manpower / Man-hour Report.
- Analysis of shop fabrication data, both piping and structural. The purpose of the level 4 Category Schedule is to set up an overall monthly project status.
- Prepare weekly progress report
- Steelwork status
- Fabrication status
- Steelwork erection
- Pipework erection
- Overview of module progress and pictorial view
spanr �00o��o�n style='mso-tab-count:1'>
76 PAS’s gross weight 3,000 Te
47 PAU’s gross weight 20,000 Te
Circa weights and Quantities:
30,600 Te Steelwork
670,000 WDI Pipe
7,000 M Hot Insulation
19,000 M Cold Insulation
270,000 M Electrical & Instrument Cable
7,250 No. Instruments
325 No. Equipment
- Schedule analysis including development of 8 week lookahead schedules. Creating What if scenarios based on current fabrication status, structural and piping, predicting on site start date.
- Liaise between Sub-Contract planning team regarding claimed progress and slippage.
- Analysis of shop fabrication data, both piping and structural. Providing FWW superintendents reports per shipment and module.
- Yard progress verification: analysis of Sub-Contract claimed progress against FWW verified progress.
- Baseline schedule slippage reports including: MIR slippage, shop fabrication, footing and yard assembly dates, impact to RFL dates caused by slippage.
- Summary 8 week look-ahead report communicated to FWW senior management.
- Attend Primary Yard progress meetings and communicate planning progress and issues.
- Compile daily progress report consisting of the following details: tonnage, support no. diameter inch, spool no.
- Prepare s curves for steelwork and piping supports and DB on a weekly basis and forecasted requirements
- Prepare weekly progress report
- Steelwork status
- Fabrication status
- Steelwork erection
- Pipework erection
- Overview of module progress and pictorial view
- Implement P.E superintendent fortnightly lookaheads and analysis on work fronts by priority and review resource levels.
- Develop Sub-Contract weekly schedule and implement good planning practices.
- Compile planning procedures when applicable to incorporate into Sub-Contract Project Measurement Procedure i.e GTG’s.