PLANNING ENGINEER, Bechtel international Inc., QC LNG Project

START Date: 
September, 2011
END Date: 
February, 2012

 

 

·         QC LNG is a multibillion-dollar EPC contact won by OG&C on Feb 5, 2010 - possibly the largest Lump Sum Turn Key LNG job that Bechtel has taken on!

·         Two LNG trains are being developed on Curtis Island, Queensland, AU on a 270-hectare site surrounded by an environmental buffer zone. They are to produce approximately 8.46 MTPA (million metric tons per year) of liquefied natural gas utilising the ConocoPhillips Optimised Cascade Process.

·         First LNG to use Coal Seam Gas from the Surat Basin in eastern Australia. The gas will be delivered through a 380km buried pipeline to Gladstone.

·         Modules Fabrication at Sriracha Job Site Chonburi Thailand Module Type

-          14 Cryogenic Rack, Propane Chiller

-            8 Propane Condenser

-          14 ISBL Piperack

-          44 OSBL Piperack & Jetty Modules

                Total Manhouse 6,500,000  Weight 46,641 Tonnes

 

  • Programmed of Work , Progress “S” Curve,  Manpower histogram (By trade).

·          Monitoring actual of progress comparing with BOQ 

·          Maintain and update Project schedule

·          Work variation and forecast volume 

·          Project S-Curve, Milestone schedule, 3 week look ahead program

·          Critical Shipment follow up and recovery plan preparation

·          Evaluate and produce Weekly progressive report, manning report

·          Monthly progressive / Critical milestone report and update P6

·          Scheduling time period of bid proposal.