PLANNING ENGINEER, Bechtel international Inc., QC LNG Project
· QC LNG is a multibillion-dollar EPC contact won by OG&C on Feb 5, 2010 - possibly the largest Lump Sum Turn Key LNG job that Bechtel has taken on!
· Two LNG trains are being developed on Curtis Island, Queensland, AU on a 270-hectare site surrounded by an environmental buffer zone. They are to produce approximately 8.46 MTPA (million metric tons per year) of liquefied natural gas utilising the ConocoPhillips Optimised Cascade Process.
· First LNG to use Coal Seam Gas from the Surat Basin in eastern Australia. The gas will be delivered through a 380km buried pipeline to Gladstone.
· Modules Fabrication at Sriracha Job Site Chonburi Thailand Module Type
- 14 Cryogenic Rack, Propane Chiller
- 8 Propane Condenser
- 14 ISBL Piperack
- 44 OSBL Piperack & Jetty Modules
Total Manhouse 6,500,000 Weight 46,641 Tonnes
- Programmed of Work , Progress “S” Curve, Manpower histogram (By trade).
· Monitoring actual of progress comparing with BOQ
· Maintain and update Project schedule
· Work variation and forecast volume
· Project S-Curve, Milestone schedule, 3 week look ahead program
· Critical Shipment follow up and recovery plan preparation
· Evaluate and produce Weekly progressive report, manning report
· Monthly progressive / Critical milestone report and update P6
· Scheduling time period of bid proposal.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: