PLANNING ENGINEER, Chevron , Gorgon LNG Downstream Project

START Date: 
February, 2012
END Date: 
December, 2012

 

The Greater Gorgon Area is located 200km offshore of the northwest coast of Western Australia and contains in excess of 40 trillion cubic feet of recoverable natural gas.

·         16.5m Manhours (EPC)

·         200K Tonnes overall

·         97K Tonnes of structure steel

·         97,000 Pipe Spools

·         1.5m meters cable

·         51 Module

  • Schedule analysis including development of 8 week lookahead schedules. Creating What if scenarios based on current fabrication status, structural and piping, predicting on site start date.
  • Liaise between Sub-Contract planning team regarding claimed progress and slippage.
  • Analysis of shop fabrication data, both piping and structural. Providing  superintendents reports per shipment and module.
  • Yard progress verification: analysis of Sub-Contract claimed progress against company verified progress.