Planning & Project Controls Engineer, Agip Nigeria, The NAOC-NLNG gas expansion project - T6

START Date: 
March, 2005
END Date: 
May, 2006

 

Project Controls Engineer (Contract)

Agip Oil Company                                                                              March 2005 – May 2006

Nigerian Liquefied Natural Gas (NLNG) Expansion Project

Key Project:

The NAOC-NLNG gas expansion project - T6 was intended to increase the gas production in the Nigerian fields (Swamp and Land Areas) and to collect part of the gas flow to supply the new production Train 6 (six) in Bonny Plant. A contract valued at USD$5million

Roles and responsibilities:

¨       Prepared Project Control Procedures

¨       Updated and maintained Progress Measurement System

¨       Prepared Weekly and Monthly Progress Reports

¨       Monitored Project cost, /schedule and progress trends against budgets,

¨       Coordinated and tracked NETCO personnel timesheets on weekly basis, Prepared Man-hour and Cost Reports, Prepared Project Financial Status Report (PFSR) and updated Project Document Register.

 

Key Accomplishment:

Delivered planning performance monitoring templates for various routine maintenance projects that helped fast-track quality project planning – some of these templates are still in use by the company

 

Tools used: Ms Project, Ms Office