Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Head - Planning, PETRONAS Chemical Group Berhad, Chemical Plant Turnaround

START Date: 
January, 1996
END Date: 
January, 2016

 

 

1.       February 2012 – present

 

COMPANY                :           PETRONAS Turnaround Services- TACS

 

DESIGNATION          :           Head Turnaround Plan and Prep

 

2.      March 2010 – January 2012         

 

COMPANY                :           PETRONAS Asean Bintulu Fertilizer

 

DESIGNATION          :           Senior Turnaround Engineer/QA-QC Eng

 

3.       October 2009-  March 2010

 

            COMPANY                :           PETRONAS Methanol Labuan

 

            DESIGNATION          :           Senior Turnaround Engineer

 

 

4.     Jan 2007 – September 2008

COMPANY                :           MLNG Sdn Bhd

 

PROJECT                  :           MLNG Satu- Module 1,2 3, MLNG Dua- Module 4,5,6  MLNG             Tiga- Module 7,8 LPG and Non Modular Shutdown.

 

          DESIGNATION            :           Senior Turnaround Planning Engineer/QA-QC

       

 

5.      Jan 2002 – Dec 2006

 

COMPANY                :           OGP Technical Services Son Bhd- MLNG

 

PROJECT                  :           MLNG Satu- Module 1,2 3, MLNG Dua- Module 4,5,6  MLNG             Tiga- Module 7,8 LPG and Non Modular Shutdown.

 

DESIGNATION          :           Turnaround Planning Engineer

 

 

 

 

 

 

 

6.     Dec 2001-June 2002

 

COMPANY                :           OGP Technical Services Sdn Bhd –

 

           PROJECT                   :           PETRONAS Methanol (Labuan) Sdn Bhd-

                                                Turnaround 2001-2002

 

DESIGNATION          :           Turnaround Planning Engineer 

 

 

7.      Oct 2000 -Dec 2001

 

            COMPANY                :           OGP Technical Services Sdn Bhd - Asean Bintulu

                                                        Fertilizer  Sdn Bhd

 

PROJECT                  :           Asean Bintulu Fertilizer Sdn Bhd 9thTurnaround

                                                Oct 2001

                                               

DESIGNATION          :           E & I Planner & QA/QC Engineer

 

8.     Feb 2000 - Oct 2000

 

COMPANY                :           OGP Technical Services Sdn Bhd - Petronas Fertilizer Kedah Sdn Bhd

 

PROJECT                  :           Petronas Fertilizer Kedah Sdn Bhd Turnaround

                                                Sept/Oct 2000

 

            DESIGNATION          :           Instrument/ Electrical Planner

 

 

9.     March 1994- Jan 2000

 

COMPANY                :           Titan Petrochemicals (M) Sdn Bhd

 

DESIGNATION          :           Instrument/ Electrical Planner

 

 

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000