Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

3D / 4D Planning Engineer, Arabtec Construction L.L.C., Expand Dhahran Residential Community Package 5 ( Client: Saudi ARAMCO )

START Date: 
October, 2014
Expand Dhahran Residential Community Package 5 ( Client: Saudi ARAMCO )(Project Total Value +1 Billion SAR) Ensure Project Controls systems and tools are properly used across the Program and that ProjectExecution Requirements (PERs) are adhered to. Preparation of Baseline, Revised and Recovery Schedules including resources for Engineering, Procurementand Construction Phases. Carry out assessments of Extensions of Time and the associated Cost impacts of change against baseline. Establish and implement methods for determining activity durations within assigned disciplines andspecialties Review and assess the work sequence with the total project plan in line with construction team to providetarget and forecasted schedules, in addition to analysis of schedules submitted by sub-contractors. Develops specific project codes of accounts and work breakdown structures, and recommends appropriatemodifications and revisions for new work items assigned. Producing planning reports for input into the monthly, weekly reporting process. Attendance of Client, suppliers and sub-contractors meetings.2. New King Abdul Aziz International Airport Project (KAIA)-Jeddah (Client: General Authority ofCivil Aviation “GACA – KSA” )(Project Total Value +7 Billion SAR) Prepare weekly, bi-weekly and monthly progress reports. Updating schedule with actual events on site. Prepare Impacted schedules for delaying events Preparation of Claims for Extension of Time.
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
1150