Project Control, Pizzarotti Spa, Cluj-Napoca, East Variant

START Date: 
June, 2009
END Date: 
January, 2010

Implementation of east variant ( amount of works 110 millions € ) site of Cluj-Napoca, Romania, Lot 1 & Lot 2. from Km 0+000 to Km 18+700, 2500000 m3 of earthmoving, 200000 lm of micropiles and tie-backs, 1500 lm of viaducts and two overpasses. Cost control, STR software, internship at warehouse, internship at administration department foreign branch Impresa Pizzarotti, Cluj-Napoca, Romania.

Experience Hours (Cost Management): 
1000