Quantity Surveyor, Enerrgia Infrastructure Pvt. Ltd, Storm Water Drainage Project (RCC Pipeline)

START Date: 
February, 2010
END Date: 
June, 2011

Employer

: Energia Infrastructure Pvt.Ltd

Post

: Quantity Surveyor

Period

: February 2010 to June 2011

Project

: Construction of RCC Storm Water Drainage System in the City of    Nashik under JNNURM scheme.

Client

: Nashik Municipal Corporation

Jobs and Responsibilities

  • Study Contract documents “Specifications & Drawings & BOQ and approved measurement styles.
  • Initiate proper survey to quantities from workshop drawings& compare it with original Contract BOQ.
  • Coordinate in preparing purchase order for material suppliers & subcontractors.
  • Submit & follow up QS documents to be revised & approved from the Engineer or Owner representative.
  • Prepare QS documents to site Engineer to issue the subcontractors & suppliers invoices.
  • Prepare monthly invoices based on actual approved quantities, measured & reviewed by consultant and or owner representative.

Coordinate in preparing claims based upon Variations, Change Orders & new scope.