Senior Planning Engineer, ARCHIRODON CONSTRUCTION OVERSEAS CO. (S.A.), Branch3 Pumping Stations (PS1, PS2 & PS3) at South Valley Development, SHEIKH ZAYED Canal – TOSHKA - EGYPT

START Date: 
February, 2005
END Date: 
February, 2006

Branch3 Pumping Stations (PS1, PS2 & PS3) at South Valley   Development, SHEIKH ZAYED Canal – TOSHKA - EGYPT

The Civil works of each plant are construction of: Inlet Basin, Wet Pit Structure, Pump House, Control Building, Store Room, Discharge Basin, Fence with Guard House, landscaping, and Discharge Pipelines.

 

The electro-mechanical part consists of: (17 # Centrifugal pumps with its Accessories, Motors, Gear Boxes, Motor Starters, Non-Return Valves, Control Instruments, MV & LV Panels, Overhead Cranes, Stop Logs and its Monorails (2 No), Weed Screens, Rubber Joint and its Monorail, Slip Joint, Irrigation System, HVAC System, Emergency Generator, Auxiliary Transformers, Battery Chargers, Fire Alarm System, Telephone System, Earthing, Lighting, Lightning Protection PLC's and MCC).