v  Developing Level I, II, III Schedule and Micro Schedule in Primavera & MS Projects.

v  Calculating Resource requirements like manpower and Plant & Machinery requirements for the Estimation in ITB.

v  Liquidating the Project quantitatively across the duration as per schedule.

v  Micro- scheduling (Level-4) & Plan development for the site for specific locations and specified activity.

v  WBS & RBS forDesign Drawings & Detail Construction work as per bill of quantities.

v  Cost distributing for detail baseline programme.

v  Cost Control.

v  Monitoring Weekly sub contractor work progress.

v  To prepare Technical Document Register for measure Engineering Progress Measurement.

v  To prepare Procurement Progress measurement Sheet.

v  To Prepare Construction Progress measurement Sheet.

v  To prepare Commissioning Progress measurement Sheet.

v  To prepare Milestone Progress measurement Sheet.

v  Preparation for Meeting with the Managers / Clients

v  Monitoring and executing various erections, commissioning and fabrication projects as per standards and P & I Drawings with respect to time over-runs to ensure timely execution of projects.

v  Identify and communicate potential schedule constraints to proposal team to ensure bid clarifications.

v  Liaising with various site departments, clients, and contractors and coordinating material reconciliations for smooth functioning. Executing projects as per contract document; monitoring as per schedule/ inspection.

v  Studying drawings, plans or patterns of structures to be made as per client’s requirements; creating look heads for equipment, tools and tackles.

v  Working on succession planning of the workforce, shift management activities, appraising the member’s performance & providing feedback.

v  Resolving interpersonal issues & working towards a harmonious work environment.

v  Listing down the resource needs for projects, after considering the budgetary parameters set. Monitoring project status during the course of periodic project review meetings.

v  Progress analysis using S-Curve generation both effort wise and cost wise.

v  Review Progress with contractors/client, analyze constraints, escalate them to top management and get them solved.

v  Productivity analysis of manpower skill wise and taking necessary action if found under performing.

v  Post award review the contract for schedule and commercial parameters to validate/ compare with the original submitted documents

v  Report generation on daily and weekly basis for the entire complex speaking on Achievements, Critical Issues, Schedule Analysis, Progress Analysis, Front Analysis, Equipment Analysis and Manpower Analysis.

v  Presentations to Management on fortnightly basis on Schedule, Progress, Issues and Resource requirements.

v  Developing and implementing key strategies for the purchase of materials from global sources; achieving cost reduction in procurement, packaging and shipping.

v  Coordinating with external agencies for techno-commercial negotiations, contract documents, cost estimates, including billing, variation proposals, etc.

v  Identifying and developing potential vendors / suppliers for achieving cost effectiveness; assessing performance of the vendors based on their competitiveness, financial capabilities and productivity.

v  Preparing tenders to sub contractors, evaluation of offers, techno-commercial discussion & finalization of contract in view of project schedule.

v  Maintaining contract bills (as per Work Order), Debit and Credit Notes.

v  Settling of all techno-commercial disputes / clarifications during execution of project.