Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Assistant Planner or Junior Planner, Bonatti SPA, Saudi Aramco Projects Petrochemical (Oil & Gas)

START Date: 
October, 2010

Ø  BONATTI S.P.A KSA BRANCH

General Contractor Oil / Gas / Petroleum

Position:  JUNIOR PLANNING ENGINEER

October 16, 2010- Present

 

      Job Description:

1. Monitor work progress with respect to the approved schedules/milestones.

2. Perform schedule updating & review (PRIMAVERA 3.0 & 6.0). Update S-Curve     per area/system/discipline. Run tabular & graphical reports in weekly and monthly basis.

3. Perform monthly progress invoice to proponent/client.

4. Understand all project costs including material, personnel, and equipment cost. Check subcontractor progress & service invoice, evaluates unit rate as per Purchase Order / Contract.

5. Create database as per contract. Maintain, organize and update datasheets of resources use.

6. Participate in department activities for continual improvement in the project control & services.

7. Participate in project review meetings & constant communication with the client (Saudi Aramco).

8. Preparation of reports as required by PMT’s, Project Controls related reports, Saudization, or required by client.

 

Projects:

1.   Upgrade Abu Ali Plant

(Saudi Aramco Project)

Jubail KSA

Project includes the Upgrade of the existing Water Injection Pumping (WIP), of the Saltwater Disposal System (produced water) and of the Distributed Control System (DCS/SCADA), located inside the existing Abu Ali Plant approximately 60 Km north of Jubail.

Ø  Upgrade the Water Injection Pumping (WIP) System

Ø  Upgrade the Saltwater Disposal System

Ø  Upgrade the Distributed Control System (DCS)

 

2.   Upgrade Flare System at Uthmaniyah and Shedgum Gas Plants

(Saudi Aramco Project)

Al Hofuf Ksa

Project includes the development of complete detail engineering, the procurement of all materials, other than FGRS and Nitrogen

Generation Units provided directly by Saudi Aramco, and all required

civil, structural, mechanical, piping electrical, communication

instrumentation and control systems works for the installation of the

FGRS and the Nitrogen Generation Unit

ØInstallation of Flaring Gas Recovery System (FGRS)

ØInstallation of new Nitrogen Generator Unit (NGU)

ØInstallation of new Flare Injection Pilot System

 

3.   Upgrade Firewater Juaymah NGL & Fractionation (JNGLF)

(Saudi Aramco Project)