Planning Engineer / Scheduler, Construtora Norberto Odebrecht, STEP Pumping Station Project , Abu Dhabi, UAE

START Date: 
May, 2012

 

  • Preparation of project master schedule (Resource & Cost loaded), using Primavera 6 Rel. 8.2.
  • Integration, Monitoring and Controlling of Subcontractor Schedules
  • Preparation, issuance and monitoring of 3 months and 3 weeks look ahead plan for site execution.
  • Preparation and discussion of variance analysis based on the plan and actual progress.
  • Development of project progress measurement system for monitoring and control.
  • Preparation of manpower and equipment deployment plans.
  • Coordination with Client, Engineer & subcontractors.
  • Integration, Monitoring and Controlling of Subcontractor Schedules
  • Preparation of project execution strategy; including mobilization of resources, reporting procedures and finalization of specific control procedures.
  • Preparation of Resource histograms
  • Integration of Project master Schedule, project Budget. Cost Structure and Price (billing) Schedule.
  • Analysis and review of Cost and Price Structure.
  • Attending and Preparation of MOM of weekly internal and Client/Engineer Meetings
  • Performing, analyzing and preparation of reports based on EVA, S Curve and KPI’s such as SPI, CPI, and SV, CV.