Planner / Project Manager (Dam project), NIMROKH, Darab DAM
START Date:
September, 2000
END Date:
September, 2010 - Coordinated all aspects of the planning and scheduling functions across all work locations
- Integrated schedules of all involved parties within the overall EPC master schedule
- Developed progress measurement systems covering engineering, procurement, and construction progress
- Developed and implemented procedures required for achieving effective project control
- Validated the percent of completion of all involved parties
- Assessed financial status of project using EVM technique and established future budget
- Interfaced with all stakeholders on project about schedule and controls related activities
- Performed periodic project schedule risk analysis
- Performed Cost-Benefit analysis and also time and cost trade-off
- Developed and implemented a change management system
- Participated in the value engineering team and facilitated the meetings
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: