Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Project Manager, Stonewall Contracting Corp., Hospitals, Transit, and Court facilities

START Date: 
April, 2003
END Date: 
May, 2005

Managed the Contractor's P3 and Expedition systems as well as interface to Prolog-Web.  Supervised all members and functions of the project management and field team as well as Esimating group and bid preparation. Provided Executive oversight for all projects, developed and ran monthly financial projections and reports, and ran all project financials through Expedition. Iimplemented Timberline Accounting for the company. Developed and presented project schedules and served as Master Scheduler on IMS for Hospital project. Developed and negotiated Change Orders and developed Contractor Claims for Equitable Adjustment on Time and Cost impacts.  Managed projects in Hospitals, Transit, and Court facilities.