Planning Engineer, Costain Oil, Gas & Process, Various

START Date: 
June, 1986
END Date: 
March, 1994

Planning Engineer

Responsible for the preparation of Level 1 Summary & Level 2 Critical Path Networks and Bar charts for Engineering, Design, Procurement and Construction. Manpower loading and the production of histograms and 'S' curves on New Project Tenders for Cryogenic, Gas & Chemical Plants. Compilation of Cash flow analyses for tenders to the value of £250 million involving Engineering, Design Procurement and Construction Projects. The Planning, Monitoring, Progress Measurement, Trend Analysis, Man-hour  & Resource Forecasting for current projects. Production of Level 4 discipline Progress Worksheets, Resource Histograms, 'S' curves, Equipment & Material Schedules, Level 1,2,3 Critical Path Networks Bar charts for various Cryogenic, Gas & Chemical Plants including Modularised Nitrogen Plants, LiN/LOx/LAr Plants and Purge Gas Recovery Units.  

Junior Planning Engineer

Assisting senior planning engineers in the production of level 3 programmes, procurement schedules and level 4 progress measurement schedules and monthly status reports.