Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Planning Engineer, ABB, JG Summit PE Capacity Expansion Project

START Date: 
April, 2013
END Date: 
May, 2014
  • Develop and forecast project schedule to achieve contract completion
  • Monitor material shortage at site
  • Submission of weekly Project Progress Report and highlight area of concerns
  • Claim of Monthly Progress to client with supporting document and photos
  • Review subcontractor’s Progress Claim
  • Monitor completion amount versus Contract amount 
Experience Hours (Planning & Scheduling): 
2300