Planning Engineer, TUCN - Total Upstream Company of Nigeria, AKPO & USAN Operations

START Date: 
March, 2009
END Date: 
February, 2016
  •  Maintain ECP Integrated Schedule which contains:
  • Carry-over/Completion works
  • Site Modifications Requests
  • Notification & request for assistance works
  • Punch Lists
  • Subsea activities – OIMR Vessels following Drilling sequence for installation of Xtrees, Jumpers & Flying leads
    • AKPO Partial Shutdown schedule preparation & progress execution monitoring in Oct. 2010.
    • AKPO Full-Field Shutdown Schedule preparation & progress execution monitoring in Oct./Nov./Dec. 2012.
    • USAN Emergency Shutdown Schedule preparation & progress execution monitoring in May/June 2013.
    • Weekly Dashboard(KPI) and Monthly Reports preparation
    • Subcontractor coordination
    • Schedule & Progress monitoring of projects
  • AKPO WHRU permanent repair
  • AKPO Exchangers inspection & repairs