Senior Planner, B&M McHugh, Various NWR Projects
B&M McHugh SENIOR PLANNING AND PROJECT MANAGEMENT CONSULTANT |
Oct 2011 – Feb 2012 |
Building, Civil and Environmental Contractor for both major and minor works: East Anglia, Kent, Sussex, Wessex regions
· Recruited as a retained specialist, with a turnover of c.£20M and 100 staff, focusing on railway infrastructure
Channel Tunnel Rail Link Drainage & CCTV Project (£400K)
· Developed a Primavera Project Plan to achieve clearance of all parts of the tunnels, involving two drainage clearance teams, a CCTV surveying team.
· Performed test shifts, booked 120 possessions to cover all works and attending weekly possession planning meeting, adapting work locations and structures as required to drive project progress
· Reviewed plans iteratively and revised work activity schedules for issue to site managers
· Issued progress reports to clients, including updated P6 cost loaded programme with baseline variance, KPIs and amended possession schedule
Accomplishment
· Project completed to specification, 2 months ahead of schedule and under budget
Somerleyton and Reedham Swingbridges Project (£1.1M)
· Complex project to repair corroded steelwork, with PWAY removing and reinstating ballast, track, sleepers and S&T renewing signalling components
· Managed project initiation phase, coordinated ongoing site meetings with client and subcontractors, produced a daily project summary and created project completion documentation and associated governance materials
Accomplishments
· Implemented a complex 9-day, 24/7, P6 Programme to coordinate activities and ensure steelwork and Network Rail’s PWAY met deadlines and specifications and modelled scenarios of the P6 Plans for contingency planning and risk mitigation
B&M McHugh PROJECT MANAGER & SENIOR PLANNER | Aug 2007 – Oct 2011 |
· NETWORK RAIL Project –Anglia Minor Works (£20M) (May 07 – Oct 11) - Set up satellite office with Lead Project Manager
Accomplishment
· Managed multiple possession-dependent projects, involving many external variant factors, timeline and resource constraints