Senior planning engineer, Ignalina Nuclear Power Plant, Decomissioning of INPP

START Date: 
November, 2009
END Date: 
December, 2012

Integrated decommissioning Program (Mega-project) activities maintaining (1-st and 2-d levels):

  • Base line (BL) creation and renewing for 2-d level, 
  • Work package progress estimation adjustment.
  • Contractors schedules and milestones integration in Integrated decommissioning Program
  • Monthly actual data collection and input,
  • Control of actual data import from accounting and timesheet systems. 
  • Schedule updating to data date
  • Logic scheme, dependences, critical path monthly observation and analysis,
  • Variances from Base Line observation, causes analysis carrying out and reporting to planning department chief
  • Status report data preparation and distributing to reporting group.
  • Remaining  budget recalculation based on up-to date calculation parameters (1 time per 2 years)
  • Cost control based on earned value method
  • Communication with all kind of company staff from decommissioning service director to foremen.

Planning group activities coordination and technical support (5 people, all Primavera

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
1550