START Date:
December, 2000
I participated on different projects as Project Controls engineer, key projects are highlighted below;
A.Kaduna Refinery & Petrochemical (Turn Around Maintenance)-USD214Million
Lead Project Controls Engineer
21 projects were executed under the KRPC TAM
I was involved in preparing the final cost estimates for these projects. Other functions performed were;
• Construction supervision
• Cost Estimating
• Prepare and updating schedules