DRAG display on Activity Window

2 replies [Last post]
Rafael Davila
User offline. Last seen 20 hours 2 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Vladimir,

I am missing DRAG on the Calculated Data Tab, I believe it shall also be there as it is a very convenient view, frequently better than looking on a table with many columns. I believe it would be very convenient to disclose on the same line, next to DRAG value the calendar used.

It also occurs to me it might be convenient to have a Tab for Calculation Settings where it would be displayed if calculations for DRAG,  Super & Flex are on/off, and any other settings of concern such as if the displayed values under Calculated Data Tab are from a resource leveled run or not. Here the calendar used for DRAG calculation can be shown, an alternative to consider.

Best Regards

Rafael

Calculated Data Tab photo Calculated Data_zpsx4cs6eg2.png

DRAG Calendar photo Drag Calendar_zpsqcnvsdsv.png

Replies

Rafael Davila
User offline. Last seen 20 hours 2 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

GREAT!

Thank you Rafael,

we will add DRAG value to the activity properties window.