Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Negative Schedule Variance with positive cost variance

1 reply [Last post]
Shafeek K A
User offline. Last seen 8 years 18 hours ago. Offline
Joined: 6 May 2016
Posts: 2
Groups: None

Hi,

I understand that having a negative schedule variance with a positive cost variance is a rare case scenario. Could you please cite me a practical situation where this could be possible ?

 

Thanks.

Replies

When works were done slower than expected but actual expenses are lower than planned.

Why did you place your post in the risk forum?