Negative Schedule Variance with positive cost variance

1 reply [Last post]
Shafeek K A
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 6 May 2016
Posts: 2
Groups: None

Hi,

I understand that having a negative schedule variance with a positive cost variance is a rare case scenario. Could you please cite me a practical situation where this could be possible ?

 

Thanks.

Replies

When works were done slower than expected but actual expenses are lower than planned.

Why did you place your post in the risk forum?