Filter Out Activities Whose Resources are over allocated

1 reply [Last post]
Galav Dani
User offline. Last seen 6 years 7 weeks ago. Offline
Joined: 6 Aug 2014
Posts: 4
Groups: None

Hii All..

 

please soggest me how to filter out all such actvitiies which having over allocated resources for any project? 

Replies

Zoltan Palffy
User offline. Last seen 3 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in p6 create a new code for overallocation

go to view show on bottom resource usage profile

and look at the time frame where the overallocation is occuring and the look for those activitie that are occuring in the time frame of the overallocation

give each of the activites that are occuring during the overallocation time frame the new code that you just made

now filter on that new code