JORGE FIERRO
User offline. Last seen 14 years 8 weeks ago. Offline
Joined: 11 Nov 2003
Posts: 11
WHICH IS THE TYPICAL PACE (PROGRESS (%) PER MONTH) THAT CAN BE CONSIDERED FOR A REFINERY PROJECT, WITHIN THE NORMAL PARAMETERS (SINGLE SHIFT, THIRD WORLD COUNTRY, NO SEASONS, ETC.....).

THANKS!!!

Replies

Jay S
User offline. Last seen 11 years 5 days ago. Offline
Joined: 10 Jun 2008
Posts: 36
It all goes about money.

How fast can you spend it.

To Spend 17 M in 18 Months is a slow project.

I Have been on Project.

1.8 B 36 Month (Engineering had to be done in 5 country’s / Fabrication in another & Construction in another

100 M 7 Month All in One Country

360 M 12 Months All In One Country

25 M = 8 Months all in One Country.

Some times it is not possible to spend money fast enough.


So to answer it quickly if a Project Duration is 20 Month 3 to 7 % per Month

If it is 10 Month 7 to 14 % per Months





JORGE FIERRO
User offline. Last seen 14 years 8 weeks ago. Offline
Joined: 11 Nov 2003
Posts: 11
Ian Thanks.

These figures gave me a good idea.

Jorge
Ian Thomson
User offline. Last seen 6 years 47 weeks ago. Offline
Joined: 30 Sep 2003
Posts: 19
What sort of project? T/A involvement. No T/A Involvement
Our major project worth 17 Million US dollars with no turnaround involved took 18 months.

8 months to 10% design mainly, 11 months to 20%, then almost 10% a month to completion. Does that help?