Extended Power Uprate project

1 reply [Last post]
Galing Galing
User offline. Last seen 17 years 26 weeks ago. Offline
Joined: 29 Oct 2007
Posts: 47
Groups: None

Hi fellow Planners,

Can anyone kindly help me with a sample WBS construction for nuclear plant EPU project? I would greatly appreciate it.

Thanks,

ton-ton

Replies

Mike Testro
User offline. Last seen 44 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Galing

You are asking for the "holy grail" of planning.

I have never done nuclear and anybody who has is not going to give it to you on request.

You have to have built it before you can plan it.

If you have not built it before then ask for guidance from those around you who have.

If you have control of the software then as always with planning:

Start from the beginning - set the activities in sequence -link them up logically.

It is not difficult.

Ask - Learn - Listen - Improve.

Best regards

Mike Testro