Output rates

1 reply [Last post]
James Thorpe
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 4 Sep 2005
Posts: 15
Groups: None
Hi Planners

I need most practical Output rates for Building Works( New Build school/house) of following activities with respect to area and gang/labour:

a) Flooring
b) Screed
c) Render

Please help me...

Secondly any planner send me Scaffolding schedule for new build building double storey in excel

Many thanks

Replies

Kieran Thomson
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 28 Jan 2004
Posts: 43
Groups: None
Jim

in response to your questions, any decent planner would need more specifics. I ask you..

a) flooring. What type of materials? Area? Purpose of floor? How many men?
b) Screed. How’s it supplied? Area? Access for Laying?
c) Render. How’s it supplied? Area? Access for applying?

If you ask your construction manager or consult the drawings then you may gain this info, but to truely shine then you will need to speek to the contractors, these are the boys that will be carrying out the work at the end of the day and will give you a fairly honest answer.
As for scaffolding schedules, pass it back to the QS’s, they need the exercise!!!!