Activity screen - Project summary showing by Chronilogical order

Member for

15 years 11 months

Keith,

In Group and Sort.... Group By Early Start with Montly Interval

Next Level is WBS or Project

 

Cheers

Member for

21 years 7 months

I am not a P6 user but wonder if you display the column for Early Start what is displayed for each summary bar. I would expect for finished activities the value to be cleared out and maybe the roll up value would be cleared out as well. If this is so then it is possible all projects having a single activity already finished would display a blank value for its summary bar and for purpose of sorting they have the same sorting value.

Member for

14 years

Thanks for the reply,

The issue isn't in getting the bars to summarise, it is in getting them to display in a chronilogical order on the screen....as the picture would suggest

At present it is showing Alphabetically as below

                                                January           February        March        April      May

project folder 1 (summary)           ----------

project folder 2 (summary)                                          --------------                            

project Folder 3 (summary)                                                            --------------

Project Folder 4 (summary)                       --------------                                     

 

It would be as chronilogical as below

 

                                                January           February        March        April      May

project folder 1 (summary)           ----------

project folder 4 (summary)                        --------------                            

project Folder 2 (summary)                                         --------------

Project Folder 3 (summary)                                                            --------------

Member for

15 years 11 months

Keith,

Try using Bars... Options.... Collapsed Bars.... seclect Collapsed to Individual Bars to minimize Space.