I am not a P6 user but wonder if you display the column for Early Start what is displayed for each summary bar. I would expect for finished activities the value to be cleared out and maybe the roll up value would be cleared out as well. If this is so then it is possible all projects having a single activity already finished would display a blank value for its summary bar and for purpose of sorting they have the same sorting value.
Member for
14 years
Member for14 years
Submitted by KGRobertson82 on Fri, 2013-02-15 10:03
The issue isn't in getting the bars to summarise, it is in getting them to display in a chronilogical order on the screen....as the picture would suggest
At present it is showing Alphabetically as below
January February March April May
project folder 1 (summary) ----------
project folder 2 (summary) --------------
project Folder 3 (summary) --------------
Project Folder 4 (summary) --------------
It would be as chronilogical as below
January February March April May
project folder 1 (summary) ----------
project folder 4 (summary) --------------
project Folder 2 (summary) --------------
Project Folder 3 (summary) --------------
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Thu, 2013-02-14 19:12
Member for
15 years 11 monthsKeith,In Group and Sort....
Keith,
In Group and Sort.... Group By Early Start with Montly Interval
Next Level is WBS or Project
Cheers
Member for
21 years 7 monthsI am not a P6 user but wonder
I am not a P6 user but wonder if you display the column for Early Start what is displayed for each summary bar. I would expect for finished activities the value to be cleared out and maybe the roll up value would be cleared out as well. If this is so then it is possible all projects having a single activity already finished would display a blank value for its summary bar and for purpose of sorting they have the same sorting value.
Member for
14 yearsThanks for the reply, The
Thanks for the reply,
The issue isn't in getting the bars to summarise, it is in getting them to display in a chronilogical order on the screen....as the picture would suggest
At present it is showing Alphabetically as below
January February March April May
project folder 1 (summary) ----------
project folder 2 (summary) --------------
project Folder 3 (summary) --------------
Project Folder 4 (summary) --------------
It would be as chronilogical as below
January February March April May
project folder 1 (summary) ----------
project folder 4 (summary) --------------
project Folder 2 (summary) --------------
Project Folder 3 (summary) --------------
Member for
15 years 11 monthsKeith,Try using Bars...
Keith,
Try using Bars... Options.... Collapsed Bars.... seclect Collapsed to Individual Bars to minimize Space.