**URGENT** P6 6.2 Calandar Issues

2 replies [Last post]
John Sims
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 2 Jun 2011
Posts: 49
Groups: None

Hi Everybody,

I have an urgent tender programme I must finish ASAP and my calandar won't calculate correctly.

My base calendar is set at 8hr/day 5 days a week, all my activities that use this calendar are fine (a day = a day)

But when i try to use a 7hr/day 5 days a week it does not calculate correctly, I have set this calendar with a 1 hour lunch break so it starts and finishes the same time as my 8hr day calendar.

If i add an activity using the 7hr/day calendar and put the duration as 1 day it starts at 9am but finishes at 10am the following day.

How do i get this to finish at 5pm the same day?

If you could help me that would be great.

 

John

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

John,

The answer to your question depends upon what version of P6 you are using.  Gary gave you the answer for Versions before Version 7.  Version 7 and later can set the number of hours in a day in the calendar (if the Administrator’s setting allows this.)  Good luck!

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

John,

The reason for this is that in your admin>admin preferences>time periods options, you have 1 day set to equal 8 hours.

You could change this to 7 hours, but then you would just screw up all your activities that are on an 8hr/day caxlendar.

Better solution is to enter your durations in hours, rather than days. -e.g. for a 1 day duration on your 7h/day activities, type "7h" in the duration box.