how to generate a planned vs actual curve basis on duration ?

2 replies [Last post]
Irfan Khan
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

I m working with a schedule wich is without cost & loaded

my duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration.  thanks in advance 

Replies

Irfan Khan
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

thanks.......got it

David Kelly
User offline. Last seen 3 years 11 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

By definition to draw a curve you need two axis.  Typically in planning these axis are time and resource quantity/cost.

 

if you want to use time for both axis, you need to add a resource that equals the time.  When you add a resource to an activity the default quantity is ususally 1h/h..... Therefore you need to add the same resource to every activity in the plan.  That means the resource qauntity will equal the duration.

All P6's resource/earned curves will be based on the duration of the activities.