Export Resource/Cost Assignment to Excel format.

8 replies [Last post]
tandyo winarno
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 14 Jul 2009
Posts: 25

Dear All,

 

Would you please advise me how to export Resource/Cost Assignment shown from Assignment menu on the Directory Bar?

 

 

Thanks

Tandyo

Replies

tandyo winarno
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 14 Jul 2009
Posts: 25

Thanks a lot Arend.

I follow your guidance and it works.

 

 

Regards,
Tandyo

Arend Kok
User offline. Last seen 10 years 19 weeks ago. Offline
Joined: 19 May 2008
Posts: 38

Tandyo,

 

You can also use the report wizzard to set up the fields over the time distribution you need and then output the report to a csv file.

 

Regards,

Arend.

tandyo winarno
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 14 Jul 2009
Posts: 25

Thanks All,

 

You are right. It works.

I tried on other machine (local database) and it works.

I work in the server database and can not work for such function. 

 

Thanks

Tandyo W. 

Amit Parmar (PMP)
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

You can try exporting data to an excel sheet, using the export function. You can design the template and set the data you want to export based on filters and columns

Regards

Amit Parmar

check out my blog on Primavera at http://www.primaverablog.in

Amit Parmar (PMP)
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

What all data do you want to export from Primavera?

 

Regards

Amit Parmar

Check out my blog on Primavera at http://www.primaverablog.in

Raymund de Laza
User offline. Last seen 34 weeks 2 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi Tandyo,

I am using P6 and it works well by selecting, copy and paste. In the excel, I can see the loads in time intervals.

272
excel.png

 

tandyo winarno
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 14 Jul 2009
Posts: 25

Thanks Raymund,

I already did, however it works only for resource description shown in the screen shot at upper left while it doesn't work for the resource assignment shown in upper right (resource assignment for every month/day) 

 

 

Regards,

Tandyo

Raymund de Laza
User offline. Last seen 34 weeks 2 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Select Resources>>> Copy >>> Paste in excel.

 

Hope this will help.

 

Regards,

 

Raymund