how primavera calculate summary duration -wbs ?

7 replies [Last post]
Alaa Al haj
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

 

 

Good morning, 

 

 

i have problem when primavera 6.7 calculate the duration at summary level -wbs

as i have to change admin preference - time period

and this affect other projects

how can we let  primavera calculate duration at WBS level  for each project according to project's calendar

as example now - wbs first activity start on 2-Nov

last activity finish 2-dec

so duration should be 30 days

but it shows only 10 days

i don’t know how  

Replies

Khuong Do
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None

Hi,

I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/

niles luo
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None

hi, all

    When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.

Best Regards

Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139

in P6 version 7 ,,,,  you have to have tick a global default calender,

may next version have this option which you  wants,

michael ramos
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

make default global equals project calendar 

in p6v7 project calendar can be tick as basis of summary

Alaa Al haj
User offline. Last seen 7 years 10 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

Thanks Michael 

 

is there alternative way to avoid using default calendar

michael ramos
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

check your assigned global calendar

p6 summary duration are based on global calendar (not project)

michael ramos
User offline. Last seen 7 years 7 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

check your assigned global calendar

p6 summary duration are based on global calendar (not project)