i have problem when primavera 6.7 calculate the duration at summary level -wbs
as i have to change admin preference - time period
and this affect other projects
how can we let primavera calculate duration at WBS level for each project according to project's calendar
as example now - wbs first activity start on 2-Nov
last activity finish 2-dec
so duration should be 30 days
but it shows only 10 days
i don’t know how