Budgeted Unit for "Cash" resource

4 replies [Last post]
James bid
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Hi Guys!

I just want to know if there is a rule of thumb in computing the budgeted units for the CASH resource in each activity?

Thanks in advance.

Chris

Replies

James bid
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Hi Rodel?

My query is about the budgeted unit for Resource " Cash.cash 12208000", is there a standard in calculating the budgeted unit for this?.

I’m just curious on how to calculate.

Thanks
Rodel Marasigan
User offline. Last seen 14 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Christopher,
It seems that your resources as assigned to cost account and taken from the estimate. What is the problem with that and what is your query?
James bid
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 50
Thanks Rodel for the reply.
Here is the resource of one activity that I derived from the program .




RC-08 Resource and Role Assignments
Activity Name
Resource ID Name Cost Account Budgeted Units % Complete
CMCSMLC50 CMCSMLC50 Site Preparation Area 0
D001LB.Labor 1792
D002GA.Ganger 168
D015HVO.Heavy Vehicle Operator 700
P002GR.Grader 224
P004WL.Wheel Loader 224
P009TR4.Truck - 40 m3 112

D003CA.Carpenter 224
D04MA.Mason 112
P007JCB.JCB 56
P014HB.Hiab 4 X 2 Truck 28
Cash.Cash 12208000
Rodel Marasigan
User offline. Last seen 14 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Christopher,
What do you mean by rule of thumb in computing budgeted units for CASH resource? P6 defaults is duration * hours per unit when assigning resources.

The rule of thumbs is a guess estimate (based on experience) of how many resources will work for each activity.

Ex: Excavation: (manual)
Labor: labor/cum

Excavation: (machine)
Labor: Operator/cum
Machine: Excavator hrs/cum

Depending on location, country and soil components - norms plus contingencies can be used.