P6, forecast details

6 replies [Last post]
shaik Barkatulla
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
hi,

In p6,for one base line i need forecast start, forecast finish, forecast duration and forecast mandays columns to forecast one baseline project. whis columns shall i add in columns list to show the above.

Thx

Replies

shaik Barkatulla
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
OK..Thank you
Rodel Marasigan
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
shaik,
Project Forecast date = Current Project start date or remaining date column.
BL is a separate data so if your BL = 18 day then you can change you current Project to 10 days. Run a resource usage spreadsheet. If you need to compare the two on the resource spreadsheet, restore the BL and open together with current project and run a resource usage spreadsheet.
See sample below:
BLvsFC
shaik Barkatulla
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
Mr. Rodel,
I have BL(Baseline),i assigned and maintained BL and updating the same, now my idea is to add forecast dates and duration with forecast mandays.
In BL i have BL start, BL finish, BL Duration and Budgeted Mandays.in BL i have planned mandays for one activity 300 and the duration is 18 days. but in forecast i want to set the forecast duration 10 days. for this 10 days how much manpower required this i want show in forecast mandays column.how to add these columns in p6 window.

Regards
Rodel Marasigan
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
shaik,
Are we talking about resource and not baseline? In baseline you cannot modify dates. Current Program start and finish is the current forecast date. Can you clarify?
For resource mandays use resource usage spreadsheet. See sample below:
Resource Spread
shaik Barkatulla
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
Mr.Rodel,
This is for the BL Project start & BL Project finish, i need to add columns for forecast start and forecast finish which i can modify the dates and the same time i need to see the forecast mandays after changing the dates.. because mandays calculating with duration of total manpower given.
Rodel Marasigan
User offline. Last seen 21 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shaik,
It depends where you assigned baseline. Project Baseline or Users Primary Baseline.
If Project Baseline:
BL Project Start & BL Project Finish date
BL Project Duration ...etc..
If Users Primary then BL1... if secondary BL2...etc...