S-Curve

6 replies [Last post]
Ruel Camaquin
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
Guys,

Just like to know if, Is it possible to generate a S-Curve in a schedule that do have any resources?

Thanks in advance to those that will be responding to this query..

Cheers!

Replies

Rodel Marasigan
User offline. Last seen 1 day 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ruel,

Below link is a good approach if Project is Activity Driven. I explain 3 options that you can use.
Duration % Complete Post #3
Ruel Camaquin
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
Guys,

Thank you for the enlightment on the matter, now all i need is to convince my boss that it is not possible!

Cheers!

Ruel
joseph ador
User offline. Last seen 13 years 49 weeks ago. Offline
Joined: 29 Jan 2009
Posts: 26
Groups: None
Ruel,

you can’t produce the S-curve or histogram without any resources assigned to the project activities. As you can see by following the steps given below, you are ask to check either you will show the s-curve/histogram based on units/cost of nonlabor. materials and labor assignments. Therefore it must be primarily comes from your resources assigned.

Regards,
Josh
Ruel Camaquin
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
Guys,

Thanks for your quick response, but how about if you schedule if is just activity driven and do not have any resources?

Again thanks a lot guys!

Cheers!

Ruel
Irfan Khan
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
Ruel,

U can generate S-Curve in P6. Just follow these steps:-

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>
> Go to View > Show on Bottom > Resource Usage Profile

> Select any one resource what u defined & u wanted to show in as a S-Curve

> Right Click on the open Space Area of Histogram.

>mark the Cumulative Box for Budgeted & Actual depending on your requirments.
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

regards,,,,,





Rodel Marasigan
User offline. Last seen 1 day 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Click the link below to download the steps which is published on the other thread with same topic.
Step On How to Produce S-Curve & Histogram