% completes becomes Zero

4 replies [Last post]
Salman Ahmed
User offline. Last seen 13 years 45 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Hi all,

Please let me know what is the reason that when I input some % completion (say 20%) and schedule the project, This % completion becomes Zero.

Thanks in advance.

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Salman,

I guess you changed your remaining duration or perhaps the finish date.

This will happen if your remaining duration is greater than original duration. Try to check this and let us know.

Regards,

Arnold
Salman Ahmed
User offline. Last seen 13 years 45 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
I have done the following:

check marked the actual start, assigned the %, updated the actual units, then F9. The result after schedule goes back to zero%, actual units too becomes zero.