P6.1 Logic Report that shows Act. Cal. assignment

1 reply [Last post]
Trevor Williams
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 11 Mar 2009
Posts: 12
Does anyone have a custom Pred. / Succ. report written for P 6.1 (or similar version) that shows the following information for the activity itself, as well as each of it’s Pred.’s & Succ.’s;

- Activity ID
- Activity Name
- OD
- RD
- Start
- Finish
- Relationship Type
- Lag
- Critical
- Total Float
- Driving
- Activity Calendar

I would be very grateful if anyone could share this report if they have it.

Replies

Ian Nicholson
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 29 Jan 2010
Posts: 42
You can create this in the report wizard. Choose new report, Activities with sub-elements Predecessors and Successors and then choose your fields for each report element.

Send me a message if you can’t get it to work and I’ll send a report to you. I’m running 7.0, so the formats may not be compatible but you can still create this in 6.1.

Ian