Activity Inserting

2 replies [Last post]
Mustafa Ismayilzada
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 26
Hi there,
Activity inserting in P6 goes by +10. How can I make it adding +1 while I am inserting new activity?

Unlike in P3 -> Options -> Activity Inserting.... I can’t find Options at all :)

Thanking you all again for your help

Replies

Mustafa Ismayilzada
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 26
Thanks very much. It works.
Ferdinand U.
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
From Projects View

Project Details

Under Defaults Tab, Change the Auto Numbering Defaults Setting for Increment